Want to know Actualtests PK0-003 Exam practice test features? Want to lear more about CompTIA CompTIA Project+ (2009) certification experience? Study Approved CompTIA PK0-003 answers to Abreast of the times PK0-003 questions at Actualtests. Gat a success with an absolute guarantee to pass CompTIA PK0-003 (CompTIA Project+ (2009)) test on your first attempt.

2017 NEW RECOMMEND

Free VCE & PDF File for CompTIA PK0-003 Real Exam
(Full Version!)

Pass on Your First TRY 100% Money Back Guarantee Realistic Practice Exam Questions

Free Instant Download NEW PK0-003 Exam Dumps (PDF & VCE):
Available on:
http://www.certleader.com/PK0-003-dumps.html

Q121. – (Topic 3) 

Pre-project setup includes which of the following activities? 

A. Planning 

B. Validating 

C. Funding 

D. Closing 

Answer:

Q122. – (Topic 1) 

Given the following: 

1. Senior management support will maintain throughout the duration of the project. 

2. Technical hardware onsite is sufficient to support the new application. 

3. Network connectivity is able to support the new product. 

4. All scope changes will follow the change control process. 

Which of the following components of a scope document would BEST capture the above criteria? 

A. Assumptions 

B. Constraints 

C. Key performance indicators 

D. Objectives 

Answer:

Q123. – (Topic 1) 

A status report shows that the earned value is $50,000, the planned value is $40,000, and actual costs are $45,000. Which of the following is the SPI of the project, and is the project ahead or behind schedule? 

A. SPI = 0.89, ahead of schedule 

B. SPI = 0.90, behind schedule 

C. SPI = 1.11, behind schedule 

D. SPI = 1.20, ahead of schedule 

Answer:

Q124. – (Topic 2) 

A project is generating a lot of concern from team members who feel they do not know what customers want. This issue could have been prevented by including which of the following activities in the project kick-off meeting? 

A. Define the business risks 

B. Define roles and responsibilities 

C. Define stakeholder expectations 

D. Define high level timeline 

Answer:

Q125. – (Topic 1) 

Which of the following is required to validate a project? 

A. Problem statement 

B. Signed project charter 

C. Key project deliverables 

D. Alignment with the organization’s strategic goals 

Answer:

Q126. – (Topic 3) 

New regulations are released that affect a credit card processing system that is currently in development. Which of the following should the project manager do FIRST? 

A. Verify that the project is on schedule. 

B. Begin the change control process. 

C. Tell the project team to stop all work. 

D. Determine additional resource needs. 

Answer:

Q127. – (Topic 3) 

A project manager receives notice that a new law will soon go into effect that may impact a current project. After confirming the information, which of the following should the project manager update FIRST? 

A. Stakeholder register 

B. Risk register 

C. Issue log 

D. Qualitative data 

Answer:

Q128. – (Topic 3) 

Given tasks A, B, C, and D, the project manager has determined that A must start before B, C, or D may start, but once A is started B, C, and D may be worked on concurrently. The dependency relationship between A and C is: 

A. finish to start. 

B. start to finish. 

C. finish to finish. 

D. start to start. 

Answer:

Q129. – (Topic 2) 

Which of the following tools will assist in providing a clear assessment of risks specific to the project? 

A. Risk matrix 

B. Risk register 

C. Risk profile 

D. Risk management plan 

Answer:

Q130. – (Topic 2) 

A project activity has a schedule that allows a late start on day 10 and a late finish on day 

20. The project manager has determined an early start could occur on day 7 with an early finish on day 14. Which of the following does this schedule identify? 

A. A lead 

B. A buffer 

C. A float 

D. A lag 

Answer: