Q171. – (Topic 2) 

Which of the following conflict management techniques is represented by making concessions to maintain team harmony? 

A. Smoothing 

B. Negotiating 

C. Collaborating 

D. Avoiding 

Answer:

Q172. – (Topic 3) 

A project is behind schedule and the development manager suggests fast tracking. Which of the following describes this suggested technique? 

A. Adding additional resources to ensure the tasks are completed on schedule 

B. Approving overtime so the assigned resources can complete the tasks on schedule 

C. Reducing the amount of testing to ensure the development effort can stay on schedule 

D. Overlapping tasks on the schedule rather than working on them consecutively 

Answer:

Q173. – (Topic 2) 

A project manager is working to select a hosting provider prior to the launch of a new web-based application. To reduce the impact of downtime due to catastrophic natural events, the project manager selects a provider with geographically diverse datacenters. This is an example of which of the following risk response strategies? 

A. Acceptance 

B. Avoidance 

C. Mitigation 

D. Transfer 

Answer:

Q174. – (Topic 2) 

Given the following statement: 

Based on industry standards, the average cost for implementing new hardware to each site is $5000. 

In which of the following areas should this statement be located within a project scope document? 

A. Assumptions 

B. Technical specifications 

C. Constraints 

D. Cost-benefit analysis 

Answer:

Q175. – (Topic 3) 

A project manager is concerned about the availability of remote resources on a geographically diverse project team. Which of the following topics would the project manager MOST likely address in the communications management plan to ensure risks associated with geographical separation are mitigated? (Select TWO). 

A. Informational guides for project management software. 

B. Meeting minutes from web-based collaboration sessions. 

C. Organizational charts divided by geographical region. 

D. Language and terminology standards for use on the project. 

E. Risk register entries relating to geographical and cultural norms. 

F. Information regarding time zone offsets for project resources. 

Answer: D,F 

Q176. – (Topic 2) 

Which of the following tools should be used to analyze quality issues? (Select TWO). 

A. Risk register 

B. Pareto chart 

C. Histogram 

D. SWOT analysis 

E. RACI chart 

Answer: B,C 

Q177. – (Topic 3) 

Which of the following project management tools helps identify trends? 

A. Network diagram 

B. Run chart 

C. Histogram 

D. Check sheet 

Answer: